Progress Continues on the Old Stage Road Widening

August 14, 2026
Projects & Case Studies

Fred Smith Company teams are making steady progress on the widening of Old Stage Road. The project will add two travel lanes, realign the intersection at Rock Service Road, and add turn lanes at Banks Road.

Before new pavement can be placed, crews must prepare the corridor and build the infrastructure that will support the finished roadway. The project requires extensive drainage, earthwork, curb construction, and asphalt paving, all carefully coordinated as work advances.

The full scope includes:

  • 7,300 linear feet of drainage pipe
  • 60 drainage structures
  • Approximately 20,000 tons of asphalt
  • Approximately 12,500 linear feet of curb
  • Approximately 17,000 cubic yards of earthwork

Each phase depends on detailed planning, clear communication, and teams working together safely in changing jobsite conditions.

Thank you to everyone helping move this important project forward. The progress taking shape on Old Stage Road reflects the hard work, skill, and dedication our teams bring to the job every day.

‍

Related Posts

General Update
March 26, 2019

Willow Springs High School

General Update
June 11, 2019

Seaforth High School

June 2019 Update – Fred Smith Company utility crews continue to install storm drainage on site. An underground detention system consisting of 312 individual modules will be installed covering over 20,000 SF in area.

General Update
May 16, 2024

Flatiron-Fred Smith Company 540 Joint Venture

Exciting developments are underway as the Flatiron-Fred Smith Company joint venture has officially broken ground on the latest phase of NC 540!