June 2019 Update – Fred Smith Company utility crews continue to install storm drainage on site. An underground detention system consisting of 312 individual modules will be installed covering over 20,000 SF in area. The completed tank will be a 11 feet tall and will be able to hold roughly 200,000 cubic feet of water.